Progress on the new shed at last. Here's the site levelled - the house site is to the left of, and behind the trailer.
Formwork in place - though it took a bit of pressure to get them to put in all of the holes for the piers under the columns.
Plastic moisture barrier under the reinforcing - also helps to control termites.
Pouring the concrete - all done in one day - all 15 cubic metres of it. The slab is 100mm thick, with a 200x200mm beam under all edges, and piers 300mm deep and 350x350mm square where each of the columns will go. It's 12m x 9m overall.
These two guys did all of it. Very hard work.
Nearly finished. It started raining gently just after this, then got heavier as the night progressed. We had to put covers over the two awning slabs around 7.00pm.
Most of the material for the shed was delivered the same day. The erector expects to start putting it all together around 11 June - should take about a week to put it up, weather allowing.